EDIS

Clayton Intermediate School


EDiS is soliciting bids for the above referenced project. The project consists of new school construction of approx. 84,455 sf. Work will include but not be limited to; site-work, landscaping, concrete, masonry, misc. metals, general carpentry, millwork & casework, EIFS, roofing, metal roofing panels, metal panel siding, joint sealants, waterproofing, doors frames & hardware, glass & glazing, skylights, metal studs & drywall, ceramic tile, acoustical ceilings, flooring, wood athletic flooring, athletic specialties, pre-manufactured casework, residential appliances, kitchen equipment, gym equipment, telescoping stands, elevators, fire protection, plumbing, HVAC, and electrical.

  • Start of Construction August 2010
  • Final Completion of the project is June 1, 2012
  • 8 Alternates
  • 6 Unit Prices
  • Please review the Summary of Work and Bid Form in the specification manual Volume I.

Fern Clendaniel Architects, Inc.